三峡工程导流设计
引用本文:朱永福.三峡工程导流设计[J].中国三峡建设,1996,3(4):8-9.
作者姓名:朱永福
作者单位:长江水利委员会!武汉市430010
摘    要:长江流量大、施工期通航要求高、二期深水围堰施工复杂,施工导流是三峡工程重大技术问题之一,经过近40年的设计研究,综合比较论证结果,选用明渠通航,三期导流方案。

关 键 词:三峡工程  方案研究  三期导流

Diversion Design of the Three Gorges Project
Zhu Yongfu.Diversion Design of the Three Gorges Project[J].China Three Gorges Construction,1996,3(4):8-9.
Authors:Zhu Yongfu
Abstract:Diversion construction of the Three Gorges project is one of its major technical problems for a high flow rate of the Yangtze River, high requirement for the navigation during the construction and a complicated construction of the second stage deep water cofferdam. A construction scheme,open channel navigation,three-stage diversion is chosen after forly forty year's designs, researches, and comprehesive comparisons have been made on the argument results.
Keywords:Three Gorges project Project study Third stage diversion