首页 | 本学科首页   官方微博 | 高级检索  
     

锚拉桩基础锚定板挡墙在临近已建挡墙填方工程中的应用
引用本文:兰新生,刘文刚.锚拉桩基础锚定板挡墙在临近已建挡墙填方工程中的应用[J].福建建设科技,2009(1):15-16.
作者姓名:兰新生  刘文刚
作者单位:福建省林业勘察设计院,福州,350001
摘    要:本文结合福建省某高路堤边坡锚定板挡墙工程,介绍锚拉桩基础锚定板挡墙在临近已建挡墙之上填方加高边坡的应用和设计方法。为避免新填筑边坡填土荷载对下方临近已建支挡结构的影响,锚定板挡墙可采用锚拉桩基础卸除附加土压力。实践证明这是一种技术可行且经济合理的方法。

关 键 词:锚拉桩  锚定板档墙  应用

Application of anchor breast wall with anchorage tensile pile foundation in filling project near the existing retain wall
Lan Xin-sheng.Application of anchor breast wall with anchorage tensile pile foundation in filling project near the existing retain wall[J].Fujian Construction Science & Technology,2009(1):15-16.
Authors:Lan Xin-sheng
Abstract:Combined with a high bank slope anchor breast wall project,the application and design method of anchor breast wall used in heightening slope filling near existing retain wall is introduced.The anchorage tensile pile foundation is used to avoid the influence of load on existing structure by new filled soil,which had proved to be a feasible and economic method.
Keywords:anchorage tensile pile  anchor breast wall  application  
本文献已被 CNKI 维普 万方数据 等数据库收录!