首页 | 本学科首页   官方微博 | 高级检索  
     

甘肃龙首二级水电站施工加密控制网的设计与实施
引用本文:杨少谋. 甘肃龙首二级水电站施工加密控制网的设计与实施[J]. 电网与水力发电进展, 2004, 20(2): 41-45
作者姓名:杨少谋
作者单位:陕西省水电工程局(集团)有限责任公司第三公司 陕西咸阳712000
摘    要:龙首二级水电站为中型三等工程。现代工程建筑对于其精度要求特别重要,特别是大中型水利水电枢纽综合性水利工程,为覆盖整体工程的测量、放线的控制,决定在大坝区和发电厂房区布设一条四等符合导线控制网。

关 键 词:龙首二级水电站  施工控制网建立  控制网施测
文章编号:1671-4768(2004)02-0041-05
修稿时间:2003-12-01

Design and practice of densified control grid for the construction of Longshou Ⅱ Hydropower Station in Gansu
YANG Shao-mou. Design and practice of densified control grid for the construction of Longshou Ⅱ Hydropower Station in Gansu[J]. Advance of Power System & Hydroelectric Engineering, 2004, 20(2): 41-45
Authors:YANG Shao-mou
Abstract:Longshou II Hydropower Station is an Grade three Project with middle scale. The modernized project, especially key project with large and middle scale, emphasizes the precision of construction. In order to cover with the whole project for survey and payingoff, it is determined that to lay a grid in accordance with Grade IV surveying standard, which will cover with the area of damsite and powerhouse.
Keywords:Longshou II Hydropower Station  control grid for survey and construction  implementing the surveying grid
本文献已被 CNKI 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号