沉降后浇带的设计与施工探讨
引用本文:刘朋辉.沉降后浇带的设计与施工探讨[J].施工技术,2012(Z1):131-133.
作者姓名:刘朋辉
作者单位:中国建筑科学研究院地基基础研究所
摘    要:对沉降后浇带位置的选择、浇筑时间的确定、沉降和差异沉降的计算方法和取消后浇带的相关依据等问题进行了研究。结合工程实践,分析了不同位置沉降和差异沉降的变化特征,对后浇带的提前浇注和取消后浇带的情况提出了建议。

关 键 词:后浇带  计算方法  差异沉降  浇筑

Discussion on Design and Construction of Late-pouring Belt
Liu Penghui.Discussion on Design and Construction of Late-pouring Belt[J].Construction Technology,2012(Z1):131-133.
Authors:Liu Penghui
Affiliation:Liu Penghui(Institute of Soil and Foundation,China Academy of Building Research,Beijing 100013,China)
Abstract:The issues of late-pouring belt are discussed,including position of late-pouring belt,deformation of pouring time,calculation of settlement and basis of canceling the late-pouring belt.Combined with the actual project,the variation characteristics of differential settlement are analyzed,and the condition of pre-pouring and cancelling of late-pouring belt are proposed.
Keywords:late-pouring belt  calculation method  differential settlement  pouring