大斜度桥梁斜塔钢构爬模刚度仿真和结构优化
引用本文:李建平,;阮杰,;王祥军,;杨基好. 大斜度桥梁斜塔钢构爬模刚度仿真和结构优化[J]. 机械研究与应用, 2014, 0(4): 96-99
作者姓名:李建平,  阮杰,  王祥军,  杨基好
作者单位:[1]中南大学机电工程学院,湖南长沙410083; [2]高性能复杂制造国家重点实验室,湖南长沙410083; [3]中南大学-中铁五新集团联合研究中心,湖南长沙410100; [4]中铁十局集团有限公司,安徽淮北235000
基金项目:国家教育部留学回国人员基金资助项目(编号:76084)
摘    要:以淮北相王大桥为背景,对大斜度桥梁斜塔钢构爬模进行刚度仿真分析和结构优化。通过建立钢构爬模有限元模型,并导入 Workbench14.5进行仿真分析,得出爬模危险应力集中区域及最大变形量位置。并对下侧立面爬模结构进行优化,优化后爬模整体应力分布均匀,最大应力减少约30%,保证了爬模的刚度,控制模板的变形量。为大斜度桥梁斜塔钢构爬模设计提供了参考。

关 键 词:刚度仿真  爬模  大斜度  结构优化

Stiffness Simulation and Structural Optimizing of Steel Climbing form Used in the Large Slope Bridge Tower
Affiliation:LI Jian-ping, RUAN Jie, WANG Xiang-jun, YANG Ji-hao (1, College of Mechanical and Electrical Engineering, Central South University, Changsha Hunan 410012, China; 2. State Key Laboratory of High Performance Complicated Manufacturing, Changsha Hunan 410083, China; 3. Joint Research Center of Central South University-China Railway Wuxin Group, Changsha Hunan 410100, China; 4. China Railway Tenth Group Company Limited, Huaibei Anhui 235000 , China)
Abstract:Combined the construction project of Huaibei Xiangwang Bridge, the stiffness simulation and structural optimizing of steel climbing form used in the large slope bridge tower are done. Through establishing the mode of climbing form, impor-ting the mode to the Workbench14. 5 proceeding simulation analysis to get the dangerous stress concentration area and maxi-mum deformation position of climbing form. Then the structure of downside surface climbing form is optimized. The stress of downside climbing form after optimization is uniform and maximum stress is reduced about 30% , which ensures the stiffness and control the deformation of the template. The reference is provided to the design of the climbing form used in the large slope bridge tower.
Keywords:stiffness simulation  climbing form  large slope  structural optimizing