广安市明月渠江部分斜拉桥设计
引用本文:周益云,杨烈军,冯开胜,肖仕伟.广安市明月渠江部分斜拉桥设计[J].预应力技术,2023,1(2):51-62.
作者姓名:周益云  杨烈军  冯开胜  肖仕伟
作者单位:中国华西工程设计建设有限公司, 四川成都 610031
摘    要:广安市明月渠江特大桥为预应力混凝土部分斜拉桥,主桥跨径布置为(110+210+110)m,采用墩梁塔固结体系。主梁为单箱三室截面,宽度为23m,根部截面高度为7.5m,跨中截面高度为1.6m,梁体设三向预应力钢筋,采用悬臂浇筑法施工。主塔为钢筋混凝土结构,采用矩形截面,塔高32.05 m。斜拉索为单索面双排索,全桥共设置56 对索。索鞍采用分丝管式索鞍,索鞍塔壁两侧设置双向抗滑键。本文研究结果可为后续类似工程设计提供参考。

关 键 词:部分斜拉桥    主梁    拉索    索塔    索鞍
收稿时间:2023/4/21 0:00:00
修稿时间:2023/5/17 0:00:00

Design and Analysis of a Partially Cable-stayed Bridge over the Mingyue Qujiang River in Guang'an
Yiyun Zhou,Liejun Yang,Kaisheng Feng,Shiwei Xiao.Design and Analysis of a Partially Cable-stayed Bridge over the Mingyue Qujiang River in Guang''an[J].Prestress Technology,2023,1(2):51-62.
Authors:Yiyun Zhou  Liejun Yang  Kaisheng Feng  Shiwei Xiao
Affiliation:China Huaxi Engineering Design and Construction Co., Ltd, Chengdu 610031, Sichuan, China
Abstract:The long bridge over the Mingyue Qujiang River in Guang''an, Sichuan, China is a prestressed concrete partially cable-stayed bridge with a main bridge span arrangement of (110+210+110) m constructed with a pier-girder-tower fixed system. The girder features a single-box three-chamber section, measuring a width of 23 m, a height of 7.5 m at the main pier top, and a height of 1.6 m at mid-span. The girder is reinforced with prestressed steel bars in three directions and constructed using the cast-in-place cantilever method. The main tower is a reinforced concrete structure with a rectangular cross-section and a height of 32.05 m. The bridge has a total of 56 pairs of stay cables in a single plane. Sleeve cable saddles are adopted with two-way anti-slip keys arranged on both sides of tower wall. The findings in this study serve as a reference for the design of similar projects in the future.
Keywords:partially cable-stayed bridge  girder  stay cable  tower  saddle