首页 | 本学科首页   官方微博 | 高级检索  
     

基于量子粒子群优化最小二乘支持向量机的变电站全寿命周期成本预测研究
引用本文:熊志伟,熊元新,熊一.基于量子粒子群优化最小二乘支持向量机的变电站全寿命周期成本预测研究[J].电测与仪表,2021,58(6):76-81.
作者姓名:熊志伟  熊元新  熊一
作者单位:武汉大学电气与自动化学院,武汉430072;武汉大学电气与自动化学院,武汉430072;湖北省电力公司经济技术研究院,武汉430072
基金项目:湖北省电力公司科技项目;国家电网有限公司总部科技项目
摘    要:变电站的规划设计与建设是电力工程建设的重点内容,快速的对变电站全寿命周期成本进行准确预测对变电站的建设具有指导意义.本文建立基于量子粒子群优化最小二乘支持向量机的变电站全寿命周期成本预测模型,将变电站全寿命周期内相关特征指标作为模型的输入,输出为变电站全寿命周期成本.通过仿真算例对比了QPSO优化LS-SVM,PSO优化LS-SVM,传统LS-SVM,BP神经网络4种预测模型的预测结果与相关性能指标.仿真结果表明,QPSO优化LS-SVM模型具有更好的预测精度,在变电站设计建设时能够快速准确的对全寿命周期成本进行预测评估,提高变电站建设的经济性.

关 键 词:全寿命周期成本  量子粒子群  最小二乘支持向量机  特征参数  适应度函数
收稿时间:2019/7/5 0:00:00
修稿时间:2019/7/5 0:00:00

Life Cycle Cost Prediction of Substation Based on QPPO and Least Squares Support Vector Machine
Xiong Zhiwei,Xiong Yuanxin and Xiong Yi.Life Cycle Cost Prediction of Substation Based on QPPO and Least Squares Support Vector Machine[J].Electrical Measurement & Instrumentation,2021,58(6):76-81.
Authors:Xiong Zhiwei  Xiong Yuanxin and Xiong Yi
Affiliation:School of Electrical and Automation,Wuhan University,School of Electrical and Automation,Wuhan University,Hubei Electric Power Corporation Economic and Technological Research Institute
Abstract:The planning, design and construction of substation is the key content of power engineering construction. The rapid prediction of the full life cycle cost of substation has guiding significance for the construction of substation. In this paper, a substation full life cycle cost prediction model based on quantum particle swarm optimization least squares support vector machine is established. The relevant characteristic index of the substation life cycle is used as the input of the model, and the output is the substation full life cycle cost. The simulation results are compared with the prediction results of QPSO optimized LS-SVM, PSO optimized LS-SVM, traditional LS-SVM, BP neural network four prediction models and related performance indicators. The simulation results show that the QPSO optimized LS-SVM model has better prediction accuracy, and can predict and evaluate the life cycle cost quickly and accurately during substation design and construction, and improve the economics of substation construction.
Keywords:life  cycle cost  quantum  particle group  LS-SVM  characteristic  parameters  fitness  function
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《电测与仪表》浏览原始摘要信息
点击此处可从《电测与仪表》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号