位移调节器用于端承型桩筏基础的模型试验研究
引用本文:周峰,郭亮,刘壮志,王旭东,王继果.位移调节器用于端承型桩筏基础的模型试验研究[J].岩土工程学报,2012,34(2):373-378.
作者姓名:周峰  郭亮  刘壮志  王旭东  王继果
作者单位:1. 南京工业大学交通学院,江苏 南京 210009; 2. 三江学院土木工程学院,江苏 南京 210012
基金项目:国家自然科学青年基金项目(51008159);住房与城乡建设部研究开发项目(2010-K3-4)
摘    要:位移调节器是用于调节物体支承接触点之间位移的特殊装置,可用来保证端承型桩筏基础桩–土的变形协调和共同作用。为研究端承型桩筏基础中位移调节器的设置对桩–土–筏相互作用的影响,进行了位移调节器设置前后端承型桩筏基础的室内模型对比试验。试验测量了桩身轴力、筏板沉降及桩间土反力,分析了不同荷载级别下端承型桩筏基础的荷载传递规律、整体沉降与差异沉降分布特征以及桩土荷载分担比等内容,结果表明:与常规端承型桩筏基础相比,位移调节器的设置改变了桩筏基础的荷载传递规律,顺利实现了桩土的共同作用,同时适当支承刚度的调节器可优先且充分地发挥筏底土体承载能力,优化桩土荷载分担比。结论可为进一步理论研究提供试验依据。

关 键 词:位移调节器  端承型桩筏基础  桩土共同作用  荷载传递规律  
收稿时间:2011-01-06

Model tests on end-bearing pile foundation by use of settlement adjustor
ZHOU Feng,GUO Liang,LIU Zhuang-zhi,WANG Xu-dong,WANG Ji-guo.Model tests on end-bearing pile foundation by use of settlement adjustor[J].Chinese Journal of Geotechnical Engineering,2012,34(2):373-378.
Authors:ZHOU Feng  GUO Liang  LIU Zhuang-zhi  WANG Xu-dong  WANG Ji-guo
Affiliation:1. College of Transportation Science & Engineering, Nanjing University of Technology, Nanjing 210009, China; 2. College of Civil Engineering, Sanjiang University, Nanjing 210012, China
Abstract:Settlement adjustor is a special device used to adjust the displacement between contact points of structures.The installation of the settlement adjustor can ensure the deformation coordination and the interaction for pile-soil of end-bearing piled raft foundation.In order to study the influence of the settlement adjustor on the interaction with pile-soil-raft of end-bearing piled raft foundation,laboratory model tests are performed before and after the installation of the settlement adjustor.The axial forces of pile,the settlement of raft and the raft-soil contact pressure are measured.Then,the pile-soil load transfer mechanism,the settlement and difference settlement of raft and the pile-soil load sharing ratio of end-bearing piled raft foundation under different load levels are analyzed.The results show that,as compared with the conventional end-bearing piled raft foundation,the installation of the settlement adjustor has changed the load transfer rule of piled raft foundation and achieved the interaction of pile-soil.Suitable bearing stiffness of the settlement adjustor can give priority and full play to the bearing capacity of the soil beneath the raft and optimize the pile-soil load sharing ratio.The conclusions can provide the experimental basis for further theoretical researches.
Keywords:settlement adjustor  end-bearing piled raft foundation  pile-soil interaction  load transfer rule