特克斯山口水电站转子组装工艺及经验总结
引用本文:卢朝刚.特克斯山口水电站转子组装工艺及经验总结[J].中国农村水电及电气化,2014(7):38-41.
作者姓名:卢朝刚
作者单位:新疆汇通水利电力工程建设有限公司,乌鲁木齐83000
摘    要:针对新疆伊犁特克斯山口水电站转子支架为圆盘式斜筋钢板焊接结构、工地现场配刨副立筋、磁轭装配、磁极挂装、制动环安装的特点,制定了转子组装工艺。本文对转子组装过程中各工序进行了阐述。

关 键 词:转子  磁轭  磁极  制动环

Rotor Assembly Process and Experience Summary of Turks Shankou Hydropower Station
LU Chao-gang.Rotor Assembly Process and Experience Summary of Turks Shankou Hydropower Station[J].Rural Hydropower & Electrification in China,2014(7):38-41.
Authors:LU Chao-gang
Affiliation:LU Chao-gang ( Xinjiang Huitong Hydraulic and Electric Engineering Construction Co., Ltd., Urumqi 83000, China)
Abstract:Xinjiang Ili Turks Shankou Hydropower Station rotor support is characterized by disc diagonal bar steel plate welding structure,auxiliary vertical bar equipment and shaving in the construction site,yoke assembly,magnetic pole hanging and brake ring installation.Rotor assembly process is formulated.All procedures in rotor assembly process are described in the paper.
Keywords:rotor  yoke  magnetic pole  brake ring