三峡二期工程大坝上游面裂缝处理
引用本文:许正平,李浚元. 三峡二期工程大坝上游面裂缝处理[J]. 西北水电, 2005, 0(2): 33-36
作者姓名:许正平  李浚元
作者单位:中国水电顾问集团西北勘测设计研究院,西安,710065
摘    要:三峡二期工程在上游围堰破堰进水前,发现在大坝上游面存在主要为竖向的裂缝,蓄水后将可能对大坝正常运行造成不利影响。裂缝处理的措施有:化学灌浆、嵌填止水材料、粘贴橡胶片、两侧及上下端防护。裂缝处理后,对施工质量进行了检测,布置了安全监测仪器,监测说明取得了良好效果。

关 键 词:三峡二期工程 泄洪坝段 厂房坝段 上游面 裂缝处理
文章编号:1006-2610(2005)02-0033-04
修稿时间:2004-05-18

Crack Treatment of Upstream Dam Surface in the Second Stage Works of Three Georges Project
XU Zheng-Ping,LI Jun-yuan. Crack Treatment of Upstream Dam Surface in the Second Stage Works of Three Georges Project[J]. Northwest Water Power, 2005, 0(2): 33-36
Authors:XU Zheng-Ping  LI Jun-yuan
Abstract:Prior to upstream weir breaking and water flowing into the foundation pit during the second stage works of Three Georges Project, it was found that there existed mainly vertical cracks on the upstream dam surface which might have adverse effect on the future normal operation of the dam upon impounding. Measures to treat cracks were taken such as chemical grouting, inserted sealing material, rubber waterstop, protection of both sides and upper/ lower ends. After treatment was carried out to the construction quality, and the safety instruments were arranged, which has achieved a good result.
Keywords:Second stage work of Three Georges Project  spillway section powerhouse section  upstream surface  crack treatment  