制备125I的堆照循环回路模拟系统调试
引用本文:于宁文,沈亦佳,吴宇轩,邓新荣,向学琴,罗志福. 制备125I的堆照循环回路模拟系统调试[J]. 同位素, 2018, 31(2): 104-109. DOI: 10.7538/tws.2017.youxian.042
作者姓名:于宁文  沈亦佳  吴宇轩  邓新荣  向学琴  罗志福
作者单位:中国原子能科学研究院 同位素研究所,北京102413
摘    要:利用中国先进研究堆(CARR)辐照制备125I的循环回路为全封闭的不锈钢细长管路系统。在入堆安装使用前,需对系统进行严格的调试实验,并测试系统的密封性,使其满足设计要求。本研究根据CARR的场所条件要求,设计125I制备循环回路模拟系统并进行调试,包括真空调试和氙气充气收气实验。采用长管路分段调试验证系统真空度并测定真空泄漏率;系统安装调试合格后,充入不同压力的天然氙气进行循环回收模拟实验。结果表明,设计的125I循环回路系统为细长多弯曲管路,系统密封性好,经氦质谱检漏测定值小于10-6 Pa•m3/s;天然氙气在系统中的导气实验结果表明,回收时间约为120 s,符合堆照生产125I的要求。实验结果证实了系统入堆安装调试的可行性,可为建立反应堆辐照制备125I回路系统提供参考。

关 键 词:125I制备  循环回路模拟系统  天然氙气  堆辐照  

Commissioning for 125I Production Loop Simulation System by Reactor Irradiation
YU Ningwen,SHEN Yijia,WU Yuxuan,DENG Xinrong,XIANG Xueqin,LUO Zhifu. Commissioning for 125I Production Loop Simulation System by Reactor Irradiation[J]. Isotopes, 2018, 31(2): 104-109. DOI: 10.7538/tws.2017.youxian.042
Authors:YU Ningwen  SHEN Yijia  WU Yuxuan  DENG Xinrong  XIANG Xueqin  LUO Zhifu
Affiliation:Department of Isotope, China Institute of Atomic Energy, Beijing 102413, China
Abstract:The loop system for iodine-125 production by China Advanced Research Reactor (CARR) was a set of device which was fully enclosed and long pipe system that made by stainless steel. The system must be strict installation and debugging before installation in the reactor, and it need to leak detection as well to ensure design requirements. According to the requirements of the place of CARR, the designing and debugging simulation system was primarily focused, mainly including the system’s installation, vaccum debugging and Xenon gas recovery test. The methods of subsection debugging for long pipeline and guiding gas test with the pipe system were carried out. After the installation and commissioning of the system, recovery simulation experiment of natural abundance of xenon was also carried out. The results showed that the I-125 simulation loop was a slender and multi bending pipeline. The system had good sealability and the measured value less than 10-6 Pa•m3/s of leak detection by helium mass-spectrometer leak detector. It took 120 seconds to recover the guiding natural Xenon,which could meet the design requirements . The system scheme was feasible and provided the basis for further iodine-125 production of loop circuit method by reactor.
Keywords:125I production  loop simulation system  natural Xenon  reactor irradiation  