首页 | 本学科首页   官方微博 | 高级检索  
     

高比例新能源接入电网光热发电-火电联合调峰优化控制方法
引用本文:张尧翔,刘文颖,李潇,杨美颖,周强,汪宁渤.高比例新能源接入电网光热发电-火电联合调峰优化控制方法[J].电力自动化设备,2021,41(4):1-7,32.
作者姓名:张尧翔  刘文颖  李潇  杨美颖  周强  汪宁渤
作者单位:华北电力大学 新能源电力系统国家重点实验室,北京 102206;国网甘肃省电力公司电力科学研究院,甘肃 兰州 730070
基金项目:国家电网公司科技项目(4000-201933188A-0-0-00)
摘    要:为了解决高比例新能源接入电网调峰能力不足的问题,提出光热发电-火电联合调峰优化控制方法.分析光热发电的可调节特性以及光热发电-火电联合调峰控制的可行性,基于此,提出高比例新能源接入电网光热发电-火电联合调峰优化控制模式;进而提出以系统受阻风光电最小为目标的光热发电-火电联合调峰优化控制方法.算例仿真表明所提优化控制方法可有效提高系统调峰能力以及减少受阻风光电量.

关 键 词:光热发电  调峰  高比例新能源  调度策略  火电机组
收稿时间:2020/4/4 0:00:00
修稿时间:2020/12/15 0:00:00

Optimal control method of peak load regulation combined concentrating solar power and thermal power for power grid accessed with high proportion of renewable energy
ZHANG Yaoxiang,LIU Wenying,LI Xiao,YANG Meiying,ZHOU Qiang,WANG Ningbo.Optimal control method of peak load regulation combined concentrating solar power and thermal power for power grid accessed with high proportion of renewable energy[J].Electric Power Automation Equipment,2021,41(4):1-7,32.
Authors:ZHANG Yaoxiang  LIU Wenying  LI Xiao  YANG Meiying  ZHOU Qiang  WANG Ningbo
Affiliation:State Key Laboratory of Alternate Electrical Power System with Renewable Energy Sources, North China Electric Power University, Beijing 102206, China;Electric Power Research Institute of State Grid Gansu Electric Power Company, Lanzhou 730070, China
Abstract:In order to solve the problem of insufficient peak load regulation ability for power grid accessed with high proportion of renewable energy, an optimal control method of peak load regulation combined CSP(Concentrating Solar Power) and thermal power is proposed. The adjustable characteristics of CSP and the control feasibility of peak load regulation combined CSP and thermal power are analyzed, on this basis, an optimal control mode of peak load regulation combined CSP and thermal power is proposed for power grid accessed with high proportion of renewable energy. Furthermore, an optimal control method of peak load regulation combined CSP and thermal power is proposed with the minimum system blocked wind and solar power as its objective. Case simulation shows that the proposed control method can effectively improve system peak load regulation ability and reduce the blocked wind and solar power.
Keywords:CSP  peak load regulation  high proportion of renewable energy  dispatching strategy  thermal power unit
本文献已被 CNKI 万方数据 等数据库收录!
点击此处可从《电力自动化设备》浏览原始摘要信息
点击此处可从《电力自动化设备》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号