Analytical framework for ex-post evaluation of transport projects: Lessons learnt on retrospective CBA
Authors:Silvia Vignetti  Francesco Giffoni  Chiara Pancotti  Francesca Pagliara
Affiliation:1. Development and Evaluation Unit, CSIL - Centre for Industrial Studies, Corso Monforte 15 – 20122, Milan, Italy;2. Dep. of Civil, Architectural and Environmental Engineering, University of Naples Federico II, Via Claudio 21-80125, Naples, Italy
Abstract:This study deals with the ex-post evaluation of ten major transport projects which were co-financed by the European Regional Development Fund and the Cohesion Fund in the period 2000–2013 and located across nine EU Member States. The original contribution of this study is represented by the combination of the traditional ex-post Cost–Benefit approach with a qualitative analysis. Specifically, a retrospective Cost–Benefit analysis is used to quantify the benefits and costs of the projects, then interviews to relevant stakeholders were carried out. Ex-post CBA, when appropriately implemented and integrated with qualitative evidence, represents a powerful tool for supporting decision-making processes and for policy lessons.
Keywords:Cost Benefit Analysis  decision-making process  evaluation criteria  Stakeholders Engagement
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号