三道湾水电站引水发电隧洞施工技术
引用本文:张绍松. 三道湾水电站引水发电隧洞施工技术[J]. 西北水电, 2006, 0(2): 28-30
作者姓名:张绍松
作者单位:河南省南阳市水利水电建筑工程公司,河南南阳,473000
摘    要:三道湾水电站引水发电洞围岩主层为变质砂岩夹千枚状板岩,其岩质较差,地质构造复杂,大部分为Ⅳ类围岩。对此类围岩采用“新奥法”施工方法,即一次支护,二次永久衬砌施工和灌浆处理,并在一次支护完成后进行了收敛量测。且获得了成功,保证施工顺利完成。

关 键 词:新奥法施工  锚喷支护  二次永久衬砌  灌浆处理  收敛量测
文章编号:1006-2610(2006)02-0028-03
收稿时间:2005-11-14
修稿时间:2005-11-14

Construction of power tunnels for Sandaowan hydropower station
ZHANG Shao-song. Construction of power tunnels for Sandaowan hydropower station[J]. Northwest Water Power, 2006, 0(2): 28-30
Authors:ZHANG Shao-song
Affiliation:Nanyang Hydroelectric and Architectural Engineering Company, Nanyang Henan 473000, China
Abstract:The adjacent rock of power tunnels for Sandaowan hydropower station is mainly metamorphic sandstone with phyllite slate,and its rock quality is poor with complicated geological structure.It belongs to Grade IV adjacent rock.New Austrian tunneling method was adopted for the primary support,secondary permanent lining and grouting treatment,and the convergence survey was performed after the primary support.It has obtained a successful results to guarantee smooth completion of the project.
Keywords:New Austrian Tunneling Method  shotcrete support  secondary permanent lining  grouting treatment  convergence survey  