库什塔依水电站沥青混凝土心墙坝坝体填筑施工技术
引用本文:吴宪生,郭智勇.库什塔依水电站沥青混凝土心墙坝坝体填筑施工技术[J].水力发电,2012,38(4):87-89.
作者姓名:吴宪生  郭智勇
作者单位:1. 中国水电建设集团十五工程局有限公司,陕西西安,712000
2. 新疆伊犁库克苏河水电开发有限公司,新疆伊犁,835500
摘    要:库什塔依水电站大坝为沥青混凝土心墙坝,坝体采取分期分序填筑,先进行上游围堰和坝后部分填筑,再填筑剩余坝体,填筑时遵循均衡平起的原则。填筑期间通过合理安排施工,严格进行施工现场管理,提前10天完成坝顶节点填筑工期,且评定的填筑单元全部合格,优良率达95.3%。

关 键 词:心墙坝  填筑  施工技术  库什塔依水电站

Dam Body Filling Technology of Kushitayi Asphalt Concrete Core Wall Dam
Wu Xiansheng , Guo Zhiyong.Dam Body Filling Technology of Kushitayi Asphalt Concrete Core Wall Dam[J].Water Power,2012,38(4):87-89.
Authors:Wu Xiansheng  Guo Zhiyong
Affiliation:1.Sinohydro Engineering Bureau 15 Co.,Ltd.,Xi’an 712000,Shaanxi,China; 2.Xinjiang Yili Kuke Su River Hydropower Development Co.,Ltd.,Yili 835500,Xinjiang,China)
Abstract:The dam in Kushitayi Hydropower Station is asphalt concrete core wall dam.The dam body is filled by stage and sub-sequence ways,that is,the upstream cofferdam and the downstream part of dam are firstly filled,and then the remaining.The filling follows balance principle.Through reasonable construction arrangement and strict site management,the dam filling is completed in 10 days ahead of the schedule,and the qualities of all filling units meet the requirements with an excellent rate of 95.3%.
Keywords:core wall dam  filling  construction technology  Kushitayi Hydropower Station