泸定水电站大坝填筑的特殊问题及解决办法
引用本文:李明辉,杨作才.泸定水电站大坝填筑的特殊问题及解决办法[J].水力发电,2012,38(1):41-43.
作者姓名:李明辉  杨作才
作者单位:中国人民武装警察部队水电第三总队第九支队,四川成都,611130
摘    要:泸定水电站大坝在施工过程中却遇到了廊道混凝土浇筑和坝体填筑相互干扰、廊道施工进度滞后影响坝体填筑速度、上下游坝料穿越心墙防渗体运输、如何保证坝体临时断面提前上升而不影响施工质量等特殊问题。通过采取合理进行施工布置、分区填筑、铺设穿越防渗体的临时道路、削坡法进行接缝处理等技术措施,很好地解决了这些问题,确保了大坝安全度汛、按期蓄水,保证了大坝工程进度、质量、效益达标。

关 键 词:大坝填筑  特殊问题  泸定水电站

Special Issues and Its Solutions in the Filling of Luding Dam
Li Minghui , Yang Zuocai.Special Issues and Its Solutions in the Filling of Luding Dam[J].Water Power,2012,38(1):41-43.
Authors:Li Minghui  Yang Zuocai
Affiliation:(The 9th Detachment of 3rd General Contingent of Chinese People’s Armed Police Hydropower Troops, Chengdu 611130,Sichuan,China)
Abstract:Some special issues are encountered in the construction of Luding Dam,including the interference of gallery concrete pouring and dam filling,the dam filling being delayed by gallery construction,upstream and downstream impervious material transport through core wall,and how to ensure the quality of construction not affecting by the temporary rise of some dam section.Through reasonable layout,partition filling,laying temporary road to across the impervious body,and treating joints by slope cutting,these issues are solved,the safety of dam and flood control are guaranteed,and the progress,quality and benefits of dam construction are also ensured.
Keywords:dam filling  special issue  Luding Hydropower Station