蒲石河抽水蓄能电站下库闸墩预应力锚索施工
引用本文:朱甲学,孙晓奇,高光辉,张强.蒲石河抽水蓄能电站下库闸墩预应力锚索施工[J].水力发电,2012,38(5):65-67.
作者姓名:朱甲学  孙晓奇  高光辉  张强
作者单位:中国水利水电第二工程局有限公司,北京,100120
摘    要:蒲石河抽水蓄能电站下库泄洪排沙闸闸墩预应力锚索施工中,张拉按照设计要求应进行整体张拉,主次锚束的整体张拉均分为6级进行,采取以应力控制为主,伸长值校核的操作方法;以千斤顶油压表作为张拉控制依据,以测力计作为监测预应力锚索锁定后的发展变化情况;采用低回缩锚具通过二次张拉,解决了施工难题,取得了良好的效果。

关 键 词:预应力锚索  闸墩  低回缩锚具  蒲石河抽水蓄能电站

Construction of Pre-stressed Anchorage Cable for the Gate Pier of Lower Reservoir in Pushihe Pumped-storage Power Station
Zhu Jiaxue , Sun Xiaoqi , Gao Guanghui , Zhang Qiang.Construction of Pre-stressed Anchorage Cable for the Gate Pier of Lower Reservoir in Pushihe Pumped-storage Power Station[J].Water Power,2012,38(5):65-67.
Authors:Zhu Jiaxue  Sun Xiaoqi  Gao Guanghui  Zhang Qiang
Affiliation:(Sinohydro Bureau 2 Co.,Ltd.,Beijing 100120,China)
Abstract:During the construction of pre-stressed anchorage cables for the flood discharging and sand gates in the lower reservoir of Pushihe Pumped-storage Power Station,the tensioning of main and secondary cables are overall carried out according to design,in which the tensile force is divided into six levels,and the tensioning is controlled by the tensile stress and checked by cable elongation.The oil pressure gauge of jack is taken as the control of tensioning during cable installation,and the dynamometer is taken as the monitoring of development after cable installation.The second tensioning is conducted by low retraction anchorage device to solve the construction problems,and achieves good results.
Keywords:pre-stressed anchorage cable  gate pier  low retraction anchorage device  Pushihe Pumped-storage Power Station