地铁施工竖井装配式钢结构初衬的受力分析
引用本文:孙希波,侯效毅,徐阳,叶涛,郝志宏. 地铁施工竖井装配式钢结构初衬的受力分析[J]. 地下空间与工程学报, 2022, 18(1): 281-289
作者姓名:孙希波  侯效毅  徐阳  叶涛  郝志宏
作者单位:北京市轨道交通建设管理有限公司,北京100068,中铁隆工程集团有限公司,成都610000,北京市轨道交通设计研究院有限公司,北京100068;北京市轨道交通工程技术研究中心,北京100068
摘    要:地铁施工竖井结构主要采用格栅钢架+喷射混凝土的喷锚支护结构。喷锚支护结构存在现场焊接作业量大,作业人员多,工期长及作业环境差等问题,为更好地解决竖井施工工期、成本及文明施工等问题,创新性地将装配式钢结构引入到地铁建设中,提出一种全新的施工竖井支护体系,用以替代传统的喷锚支护结构,从而有效解决与“格栅钢架+喷射混凝土”支护体系相伴的施工工期长、作业环境差等问题。从理论上分析了装配式钢结构衬砌结构受力的可行性,并在地铁学院桥站施工竖井进行了应用,该新型初衬的实施对提高行业技术水平、改善作业环境、缩短工期、提高工程质量具有重要意义。

关 键 词:地铁施工竖井  装配式钢结构  结构受力分析  数值模拟
收稿时间:2021-09-09

Stress Analysis of Prefabricated Steel Structure Primary Lining of Subway Construction Shaft
Sun Xibo,Hou Xiaoyi,Xu Yang,Ye Tao,Hao Zhihong. Stress Analysis of Prefabricated Steel Structure Primary Lining of Subway Construction Shaft[J]. Chinese Journal of Underground Space and Engineering, 2022, 18(1): 281-289
Authors:Sun Xibo  Hou Xiaoyi  Xu Yang  Ye Tao  Hao Zhihong
Abstract:The combined bolting and shotcrete structure of “grid steel frame & shotcrete” is applied in most subway construction shafts. However, such structure is involved with such issues as great workload of site welding, many operators, long construction period and unfavorable working environment. To solve such issues, including cost and civilized construction, an innovation is made to introduce prefabricated steel structure into subway construction, and a brand new shaft supporting structure is put forward to replace traditional structure, and thus gave an effective solution to relevant issues (such as long construction period and poor working environment) in the supporting system of “grid steel frame & shotcrete”. Furthermore, theoretical analysis is made on the stress feasibility of prefabricated steel lining structure, and it was applied in the construction of the shaft at Subway Xueyuan Bridge Station. This new type lining is of great significance for increasing the industrial technological level, improving the working environment, shortening the construction period and improving the construction quality.
Keywords:subway construction shaft  prefabricated steel structure  structure stress analysis  numerical simulation  