隆安县金鸡滩电厂一次主接线改造设计 |
| |
引用本文: | 周瑞祥. 隆安县金鸡滩电厂一次主接线改造设计[J]. 广西水利水电, 2009, 0(4): 44-46 |
| |
作者姓名: | 周瑞祥 |
| |
作者单位: | 广西南宁水利电力设计院,广西,南宁,530001 |
| |
摘 要: | 广西隆安县金鸡滩水电厂为了避免因系统故障或本电厂110kV母线及其所连接的设备检修或故障时。而引起3台机组全部停电,导致电厂的电能无法送出,拟将110kV单母线改为单母线断路器分段运行方式,改造后电厂的运行方式将更加可靠、灵活,更能充分发挥电厂的经济效益。
|
关 键 词: | 电厂 一次主接线 改造 设计 |
Main electrical connection upgrade design of Jinjitan HPP |
| |
Affiliation: | ZHOU Rui-xing (Nanning Water conservancy & Hydropower Design Institute, Nanning 530001, China) |
| |
Abstract: | Jinjitan Hydropower Plant is located in Longan county of Guangxi. In order to prevent the electricity output of all 3 sets of units unable to be transmitted outward due to fault of system or maintenance or failure of the 110kV busbar and the equipment connected with it, the original single 110kV bus is upgraded into bus sectionalized with circuit breaker, rendering more reliable and flexible operation and more economic benefits. |
| |
Keywords: | Hydropower Plant (HPP) main electrical connection upgrade design |