黄河保德王家滩水毁堤防工程治理方案
引用本文:赵明贵.黄河保德王家滩水毁堤防工程治理方案[J].山西水利科技,2009(3):21-22.
作者姓名:赵明贵
作者单位:山西省水利水电工程建设监理公司,太原,030002
摘    要:在黄河保德王家滩水毁堤防工程治理过程中,设计采用混凝土摩擦桩施工,该方案彻底解决了因孤山川河与黄河两股水流发生顶冲作用形成旋流掏刷基础。而造成该段堤防坍塌问题,根除了隐患。

关 键 词:方案  方法  混凝土摩擦桩

Improvement Plan of Yellow River's Levee Works Located at Wangjiatan of Baode County and Damaged by Flood
ZHAO Ming-gui.Improvement Plan of Yellow River''s Levee Works Located at Wangjiatan of Baode County and Damaged by Flood[J].Shanxi Hydrotechnics,2009(3):21-22.
Authors:ZHAO Ming-gui
Affiliation:ZHAO Ming-gui
Abstract:The cement friction piles are adopted in design and construction in the improvement process of Baode County and damages by flood. This plan bas radically solves the problem of levee collapse in this section formed by in caving base caused by rotative flow generated by direct flow impact of two streams, one of these belong to Yellow River and another one is Gushanchuan River, the hidden danger is eliminated thereby.
Keywords:plan method cement friction pile