Fuzzy Logic Approach for Activity Delay Analysis and Schedule Updating
Authors:Adriana V Ordó?ez Oliveros  Aminah Robinson Fayek
Affiliation:1Strategic Planning Engineer, Bogotá Urban Development Institute, Calle 22 No. 6–27, Bogotá, Colombia, South America.
2Associate Professor, Dept. of Civil and Environmental Engineering, Univ. of Alberta, Edmonton AB, Canada T6G 2G7.
Abstract:This paper presents a fuzzy logic model that integrates daily site reporting of activity progress and delays, with a schedule updating and forecasting system for construction project monitoring and control. The model developed assists in the analysis of the effects of delays on a project’s completion date and consists of several components: An as-built database integrated with project scheduling; a list of potential causes for delays; a procedure to categorize delays; a method of estimating delay durations utilizing fuzzy logic; a procedure that updates the schedule; and, a procedure that evaluates the effects and likely consequences of delays on activity progress. This model is of relevance to researchers since it makes a contribution in project scheduling by developing a complete approach for handling the uncertainty inherent in schedule updating and activity delay analysis. It also advances the application of fuzzy logic in construction. It is of relevance to construction industry practitioners since it provides them with a useful technique for incorporating as-built data into the schedule, assessing the impact of delays on the schedule, and updating the schedule to reflect the consequences of delays and corrective actions taken. The use of fuzzy logic in the model allows linguistic and subjective assessments to be made, and thereby suits the actual practices commonly used in industry.
Keywords:Computer aided scheduling  Construction management  Critical path method  Databases  Fuzzy sets  Project management  