首页 | 本学科首页   官方微博 | 高级检索  
     

刘家峡水库汛期动态防洪限制水位论证研究
引用本文:李继清,姚志宗,贾怀森,纪昌明,缪益平,李崇浩.刘家峡水库汛期动态防洪限制水位论证研究[J].水力发电学报,2007,26(5):1-6.
作者姓名:李继清  姚志宗  贾怀森  纪昌明  缪益平  李崇浩
作者单位:1. 华北电力大学,北京,102206
2. 甘肃省电力公司,兰州,730054
3. 二滩水电开发有限责任公司,成都,610021
4. 中国南方电网公司,广州,510623
基金项目:国家自然科学基金;武汉大学校科研和教改项目
摘    要:效益的增加不能以风险的提高为代价,科学合理地制定并从风险与效益两个方面论证刘家峡水库的动态防洪限制水位是非常必要的。据国家防总发布的《水库汛限水位动态控制试点工作意见》,基于现有黄河上游电站的工程条件和技术资料,在龙羊峡~刘家峡两库联合调度的基础上,采用库容补偿方法,探讨一种以旬为单位的动态汛限水位控制方法,建立动态汛限水位过程线,并进行其风险与效益分析论证。实例研究表明:该动态汛限水位过程线可操作性强,使用方便,在满足设计防洪标准要求的前提下,前汛期不必过早地降低水库水位,后汛期又可较快地抬升水库水位,不仅能够提高水头效益,而且更容易抓住时机尽早蓄水,提高水库蓄满率,增加发电效益。

关 键 词:水资源  动态防洪限制水位  库容补偿  风险  效益  刘家峡水库
收稿时间:2006-10-16
修稿时间:2006年10月16

Feasibility argumentation on the dynamical flood control limited water level of Liujiaxia reservoir in flood season
LI Jiqing,YAO Zhizong,JIA Huaisen,JI Changming,MIAO Yiping,LI Chonghao.Feasibility argumentation on the dynamical flood control limited water level of Liujiaxia reservoir in flood season[J].Journal of Hydroelectric Engineering,2007,26(5):1-6.
Authors:LI Jiqing  YAO Zhizong  JIA Huaisen  JI Changming  MIAO Yiping  LI Chonghao
Affiliation:1. North China Electric Power University, Beijing 102206; 2. Gansu Electric Power Co. , Lanzhou 730050; 3. Ertan Hydropower Development Co. , Chengdu 610021 ;4. China Southern Power Grid Co., Guangzhou 510623
Abstract:With scientifically reasonable argumentation on dynamical flood control limited water level of Liujiaxia reservoir,it is not only able to take full advantage of water resources in the Yellow River and exert synthetical utilization of the cascade reservoirs as soon as possible,but also to meet standard of flood control design and insure safety of reservoir.According to "Experimental Working Idea of Dynamic Control of Reservoir Flood Limited Water Level Operation",issued by Office of State Flood Control and Drought Relief Headquarters,the method "reservoir capacity compensation" is probed into the practicable dynamic controlling operation of flood limited water level of Liujiaxia reservoir and the flood-water hydrograph staged by period of ten days is established based on united operation of Longyangxia and Liujiaxia cascade hydropower stations.In the meantime,it's important to take into account of engineering conditions and technical datum of existent cascade hydropower stations on the upper reaches of the Yellow River.As to the dynamical flood control limited level hydrograph,it's pertinent and operable that the reservoir level needs not to be prematurely fallen in the former flood season and flectingly driven up in the latter flood season.Therefore,it is not only able to gain electricity benefit,but also to make the opportunity to adequately store flood water early to increase the rate of impounding reservoirs.
Keywords:water resources  dynamical flood control limited water level  reservoir capacity compensation  risk  benefit  Liujiaxia reservoir
本文献已被 CNKI 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏