基于梯形模糊数和C-OWA算子的地铁盾构施工风险评估方法
引用本文:宗秋雷,王彬,王凯,张瑉嘉,张家铭,王聪.基于梯形模糊数和C-OWA算子的地铁盾构施工风险评估方法[J].长江科学院院报,2020,37(12):98-104.
作者姓名:宗秋雷  王彬  王凯  张瑉嘉  张家铭  王聪
作者单位:1.中国水利水电第七工程局有限公司,成都 610213; 2.中国地质大学(武汉) 工程学院,武汉 430074
基金项目:中国电建科技计划项目(SZDT-1203-ZY-2018);中国地质大学(武汉)实验技术研究项目(SJ-201906);中央高校基本科研业务费专项资金资助项目(1810491A24)
摘    要:城市地铁盾构隧道施工过程十分复杂,涉及诸多潜在风险,施工控制不当将严重威胁公共安全。为有效管控地铁盾构隧道施工风险,提出了一种基于梯形模糊数和C-OWA算子赋权法的风险评估方法,将专家评价信息用梯形模糊数表示,运用模糊数运算规则计算各潜在风险因素的风险水平,运用C-OWA算子赋权法计算所得各风险指标权重,从评价体系底层因素向上逐层运算,确定各级风险指标的风险水平,依据风险矩阵进行风险等级划分。以深圳地铁12号线某盾构隧道区间为例,应用所提出的方法对风险进行评估,获取了需实施风险防范措施的潜在风险因素。实例计算表明,该方法合理可靠,处理定义模糊和涉及主观性的复杂问题相对于传统风险评估手段更具优势。

关 键 词:地铁盾构施工  梯形模糊数  C-OWA算子  风险评估  深圳  
收稿时间:2019-07-29
修稿时间:2019-10-30

A Risk Assessment Method for Metro Shield Construction Based on Trapezoidal Fuzzy Number and C-OWA Operator
ZONG Qiu-lei,WANG Bin,WANG Kai,ZHANG Min-jia,ZHANG Jia-ming,WANG Cong.A Risk Assessment Method for Metro Shield Construction Based on Trapezoidal Fuzzy Number and C-OWA Operator[J].Journal of Yangtze River Scientific Research Institute,2020,37(12):98-104.
Authors:ZONG Qiu-lei  WANG Bin  WANG Kai  ZHANG Min-jia  ZHANG Jia-ming  WANG Cong
Affiliation:1. Sinohydro Bureau 7 Co., Ltd., Chengdu 610213, China; 2. Faculty of Engineering, China University of Geosciences(Wuhan), Wuhan 430074, China
Abstract:The process of shield tunnel construction for metro is very complicated involving many potential risks. If not properly controlled, the construction will pose severe threats to public safety. In an attempt to effectively control the risks of shield tunnel construction, a risk assessment method based on trapezoidal fuzzy number and C-OWA operator is proposed. The evaluation information of experts is represented by trapezoidal fuzzy numbers, and the operational rule of fuzzy number is adopted to calculate the risk level of each potential risk factor. The risk level of evaluation indicators at all hierarchies, combined with the weight of each risk index calculated by C-OWA operator weighting method, is determined by calculating down-top of the evaluation system. The risk rating is obtained according to the risk matrix. The proposed method was applied to evaluate the construction risks of a shield tunnel construction of Shenzhen Metro Line 12, and the potential risk factors that require risk prevention measures in the project are obtained. The example shows that the proposed method is reasonable and reliable. Compared with traditional risk assessment methods, it has more advantages in dealing with complex problems involving fuzzy definition and subjectiveness.
Keywords:metro shield construction  trapezoidal fuzzy number  C-OWA operator  risk assessment  Shenzhen  