首页 | 本学科首页   官方微博 | 高级检索  
     

矿井改扩建后7秒级导线控制网的恢复与应用
引用本文:高少英.矿井改扩建后7秒级导线控制网的恢复与应用[J].陕西煤炭,2011,30(6).
作者姓名:高少英
作者单位:陕建集团设备安装工程有限公司,陕西西安,710077
摘    要:阐述了补连塔煤矿改扩建后在地面导线控制网被破坏的情况下,通过收集地面已有的数据恢复和建立地面GPS控制网,利用地面控制成果对井下导线控制网进行布设和观测,与已有的井下导线系统联测并进行平差计算,从而达到对井下已形成的巷道进行系统的改算和优化。

关 键 词:GPS控制测量  井下导线控制网  平差计算  系统改算

Recovery and application of seven-second level control network in mine reconstruction
Authors:GAO Guo-hong
Affiliation:GAO Guo-hong (Shendong Geological Survey Company of Shenhua Group,Erdos 017209,China)
Abstract:The ground conductor control network was destroyed when mine reconstructing in Bulianta coal mine. By collecting the ground existing data, constructing ground GPS control network, the underground conductor control network was layout and contacted to the underground conductor system based the ground control results. Finally systematic transformation optimization was completed for the existed underground tunnels by Adjustment calculation.
Keywords:GPS control survey  underground conductor control network  adjustment calculation  systematic transformation
本文献已被 CNKI 万方数据 等数据库收录!