首页 | 本学科首页   官方微博 | 高级检索  
     

董箐水电站垫层钢管的设计研究
引用本文:申显柱,李水生,湛正刚.董箐水电站垫层钢管的设计研究[J].电力勘测设计,2014(1):72-76.
作者姓名:申显柱  李水生  湛正刚
作者单位:贵阳勘测设计研究院,贵州贵阳550081
摘    要:水电站引水钢管末端与发电厂房蜗壳连接处存在变形应力协调问题,董箐引水钢管设计中,采用垫层钢管取代波纹管伸缩节,并进行了分析、计算研究,验证了垫层钢管能适应变形应力协调,具备伸缩节类似功能,且该结构型式可降低施工难度、缩短工期、节省工程投资,具有良好的推广应用价值。

关 键 词:引水钢管  垫层钢管  伸缩节  应力变形  董箐水电站

Design of Cushion Course Steel Pipe in Dongqing Hydropower Station
SHEN Xian-zhu,LI Shui-sheng,ZHAN Zheng-gang.Design of Cushion Course Steel Pipe in Dongqing Hydropower Station[J].Electric Power Survey & Design,2014(1):72-76.
Authors:SHEN Xian-zhu  LI Shui-sheng  ZHAN Zheng-gang
Affiliation:SHEN Xian-zhu, LI Shui-sheng, ZHAN Zheng-gang
Abstract:The joint between the end of penstock and spiral case is under deformation stress. In Dongqing hydropower project penstock with cushion course was used to take place of bellows expansion joint and related analysis and calculation were carried out. It was proved that penstock with cushion course could handle stress deformation, a function similar to joints. This way can make construction easier, shorten construction period and save investment. It's worthy of being promoted.
Keywords:penstock  penstock with cushion course  expansion joint  stress deformation  dongqing hydropower project