某水电站长发电引水系统设计和优化
引用本文:潘旭东,杨照明,郭宇.某水电站长发电引水系统设计和优化[J].水力发电,2011,37(9).
作者姓名:潘旭东  杨照明  郭宇
作者单位:新疆水利水电勘测设计研究院,新疆 乌鲁木齐,830000
摘    要:根据新疆某水电站发电引水系统的地形、地质条件,对发电引水洞Ⅱ类及ⅢA类(Ⅲ类偏好)围岩洞段取消常规的钢筋混凝土全断面衬砌,采用喷锚支护作为永久衬砌,缩短了发电洞的施工工期;参考以往工程经验,上游调压室取消了检修门,既可保证电站的安全运行又可减少工程投资。这些设计优化,可供类似的长发电引水洞工程参考。

关 键 词:发电引水洞  衬砌  喷护  调压室  优化设计  

Design and Optimization of the Long Diversion System for a Hydropower Station
Pan Xudong,Yang Zhaoming,Guo Yu.Design and Optimization of the Long Diversion System for a Hydropower Station[J].Water Power,2011,37(9).
Authors:Pan Xudong  Yang Zhaoming  Guo Yu
Affiliation:Pan Xudong,Yang Zhaoming,Guo Yu(Xinjiang Investigation and Design Institute for Water Resources and Hydropower,Urumqi 830000,Xinjinag,China)
Abstract:According to the topographical and geological conditions of a hydropower station in Xinjiang,the sections of diversion tunnel with Class II or IIIa surrounding rock are designed to be lined with shotcrete and anchor rod as a permanent lining instead of conventional reinforced concrete full-face lining.The lining optimization shortens the construction period.Based on existing engineering experiences,the service gate for the upstream surge chamber is cancelled,which can not only guarantee the safe operation o...
Keywords:water diversion tunnel  lining  shotcrete support  surge chamber  design optimization  