三峡电站流量变率对两坝间通航水流影响的三维计算分析
引用本文:黄明海,李飞,史德亮,邢领航,唐文坚. 三峡电站流量变率对两坝间通航水流影响的三维计算分析[J]. 长江科学院院报, 2013, 30(7): 48-52. DOI: 10.3969/j.issn.1001-5485.2013.07.010
作者姓名:黄明海  李飞  史德亮  邢领航  唐文坚
作者单位:1.长江科学院 水力学研究所,武汉 430010;2.长江水利委员会 a.规划计划局;b.国际合作与科技局,武汉 430010
基金项目:国家自然科学基金资助项目(11202037);中央级公益性科研院所基本科研业务费专项(CKSF2012026SL,CKSF2013024/SL,CKSF2013028/SL);“十二五”国家科技支撑计划课题(2012BAK10B04)
摘    要:三峡至葛洲坝两坝间航道曲折多变、水流条件复杂,三峡电站在泄洪和日调节时产生的非恒定流,使得两坝间的航行条件更为复杂。通过建立两坝间通航水流三维数学模型,针对电站机组开启过程下泄流量变率产生的非恒定流对两坝间河段通航水流条件的影响,开展了计算分析研究。计算分析了三峡电站机组不同开启时间和不同开启流量情况对典型河段水面比降、表面流速产生的影响及其变化规律。研究结果表明:机组开启时间变化情况下,通航最困难河段水面比降增幅随机组开启时间缩短而加大,但最大表面流速线性增大;机组开启流量变化情况下,水面比降和最大表面流速随下泄流量线性增大。

关 键 词:两坝间  流量变率  通航水流  三维模型  
收稿时间:2012-08-14
修稿时间:2013-07-03

Three Dimensional Computation of the Influence of Flow Variation Caused by Three Gorges Powerplant on the Navigation Condition Between TGD and Gezhouba Dam
HUANG Ming-hai,LI Fei,SHI De-liang,XING Ling-hang,TANG Wen-jian. Three Dimensional Computation of the Influence of Flow Variation Caused by Three Gorges Powerplant on the Navigation Condition Between TGD and Gezhouba Dam[J]. Journal of Yangtze River Scientific Research Institute, 2013, 30(7): 48-52. DOI: 10.3969/j.issn.1001-5485.2013.07.010
Authors:HUANG Ming-hai  LI Fei  SHI De-liang  XING Ling-hang  TANG Wen-jian
Affiliation:1.Hydraulics Department, Yangtze River Scientific Research Institute, Wuhan 430010, China;2.Bureau of Planning, Changjiang Water Resources Commission, Wuhan 430010, China;3. Bureau of International Cooperation, Changjiang Water Resources Commission, Wuhan 430010, China
Abstract:The waterway between Three Gorges Dam (TGD) and Gezhouba Dam is tortuous and varied. The unsteady flow caused by the discharge and daily regulation of TGD powerplant complicates the navigation conditions between the two dams. We established a 3-D mathematical model to simulate the unsteady flow caused by the operation of power units. By analyzing the calculation results, we obtained the variation regularity of water surface water gradient and surface water velocity in typical segment between the two dams in the presence of different operation time s and discharges. Results show that with the shortening of the operation time of power units, the increment of surface water gradient in the most hazardous segment intensified, and the maximum surface velocity increased linearly; while with the increase of discharge, the surface water gradient and maximum surface velocity increased linearly.
Keywords:waterway between Three Gorges dam and Gezhouba dam  flow variation  navigable flow condition  3D mathematical model