首页 | 本学科首页   官方微博 | 高级检索  
     

堆石坝面板混凝土施工期温度和应力全坝段仿真分析
引用本文:陈守开,马大仲,郭利霞,郭磊.堆石坝面板混凝土施工期温度和应力全坝段仿真分析[J].华北水利水电学院学报,2012,33(3):9-12.
作者姓名:陈守开  马大仲  郭利霞  郭磊
作者单位:1. 华北水利水电学院,河南郑州,450011
2. 河南华北水电工程监理有限公司,河南郑州,450011
基金项目:国家自然科学基金资助项目
摘    要:针对堆石坝面板混凝土易开裂问题及其结构特点,开展了面板混凝土施工期温度和应力变化规律的仿真研究.依托某混凝土面板堆石坝工程,建立了三维仿真计算网格;采用三维不稳定温度场和应力场的有限元仿真计算程序,对堆石坝面板全坝段施工过程的温度和应力进行了动态仿真计算和分析.结果表明,堆石坝面板施工期内部拉应力较大,且最大拉应力出现在最大温降龄期;此外,面板短间歇面施工期拉应力较小,长间歇面在上层混凝土浇筑后拉应力较大.

关 键 词:混凝土面板  面板堆石坝  温度  应力

Numerical Analysis of Temperature and Stress on Concrete Slab of CFRD during Whole Dam Construction
CHEN Shou-kai , MA Da-zhong , GUO Li-xia , GUO Lei.Numerical Analysis of Temperature and Stress on Concrete Slab of CFRD during Whole Dam Construction[J].Journal of North China Institute of Water Conservancy and Hydroelectric Power,2012,33(3):9-12.
Authors:CHEN Shou-kai  MA Da-zhong  GUO Li-xia  GUO Lei
Affiliation:1(1.North China Institute of Water Conservancy and Hydroelectric Power,Zhengzhou 450011,China; 2.Henan North China Hydropower Project Supervision Co.Ltd.,Zhengzhou 450011,China)
Abstract:In view of the crack problem of concrete slab of the concrete face rockfill dam(CFRD) and its structure features,numerical analysis of the variation law of temperature and stress in concrete slab was carried out.Based on a CFRD project,through building three-dimensional computational grids,the temperature and stress field in slab of the CFRD during the whole dam construction process were numerically simulated and analyzed by a three-dimensional finite element simulation program.The results show that the large tensile stress occurs in the interior of slab,and the maximum is appeared when the maximum temperature drop happens.In addition,the tensile stress of slab short intermittent surface is small,and the long intermittent surface is large after the upper concrete is poured.
Keywords:concrete slab  CFRD  temperature  stress