首页 | 本学科首页   官方微博 | 高级检索  
     

660MW机组基建过程中对脱硫装置的改进
引用本文:张荣发.660MW机组基建过程中对脱硫装置的改进[J].江苏电机工程,2014(2):72-74,78.
作者姓名:张荣发
作者单位:江苏射阳港发电有限责任公司,江苏盐城224345
摘    要:国家环保部对脱硫装置取消旁路烟道提出明确的要求,2011版《火电厂大气污染物排放标准》对SO2排放提出了更高的标准。某电厂660 MW机组在建设过程中,积极采取措施,对相关系统进行配套优化,提高机组的可靠性和脱硫装置的性能保证值,避免机组投产后的后期改造,节约了投资成本,并保证了脱硫设施满足环保执行标准提高的需要。

关 键 词:燃煤机组  脱硫装置  取消旁路  提升性能  措施

Improvement of Desulphurization System of 660 MW Power Unit During Construction Process
ZHANG Rongfa.Improvement of Desulphurization System of 660 MW Power Unit During Construction Process[J].Jiangsu Electrical Engineering,2014(2):72-74,78.
Authors:ZHANG Rongfa
Affiliation:ZHANG Rongfa (Jiangsu Sheyanggang Power Generation Co. Ltd., Yancheng 224345, China)
Abstract:The State Environment Protection Department has made clear requirement for removing the bypass flue in the desulfurization systems. The 2011 version of Emission Standard of Air Pollutants for Thermal Power plants has also imposed higher demand on the sulfur dioxide emissions. In the construction process of one 600 MW power unit, active measures were adopted to optimize the related systems and improve the reliability of generation units. This can ensure that no more large reform is needed in future. The investment cost is reduced, the adopted desulphurization system, however, can meet higher demand.
Keywords:coal-fired power unit  desulphurization equipment  removing bypass system  performance improvement  measures
本文献已被 CNKI 维普 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号