首页 | 本学科首页   官方微博 | 高级检索  
     

地区电网计及备自投的N-1静态安全分析快速计算方法
引用本文:潘凯岩,谭大帅,赵勇,李俊格,高强. 地区电网计及备自投的N-1静态安全分析快速计算方法[J]. 电力系统自动化, 2015, 39(24): 122-128
作者姓名:潘凯岩  谭大帅  赵勇  李俊格  高强
作者单位:东方电子股份有限公司, 山东省烟台市 264000,东方电子股份有限公司, 山东省烟台市 264000,东方电子股份有限公司, 山东省烟台市 264000,广州供电局有限公司, 广东省广州市 510620,广州供电局有限公司, 广东省广州市 510620
摘    要:地区电网由于其自身的特点在进行实时N-1分析时通常会引起大量的备自投动作,传统的方法在进行N-1分析时,先对具体的故障进行模拟,然后进行拓扑分析,再进行考虑备自投动作后的拓扑分析。整个过程涉及频繁的开关操作从而要进行大量的拓扑计算。根据地区电网的特点提出了两种考虑备自投的实时N-1计算方法,该方法分别是通过供电路径搜索或预先建立N-1故障与动作的备自投的映射关系,在潮流校核过程中通过负荷转移的方法将负荷从工作母线转移到备用母线来模拟备自投的动作。该方法不需要改变电网的基本拓扑关系,从而大大地缩短了计算时间,现场运行情况表明所提出的方法是可行的,可以更高效地对电网进行N-1分析。

关 键 词:静态安全分析   N-1   负荷转移   备自投   供电路径搜索
收稿时间:2015-03-03
修稿时间:2015-07-01

A Fast Computing Method of N-1 in Static Safety Analysis Considering BATS in Regional Power Grid
PAN Kaiyan,TAN Dashuai,ZHAO Yong,LI Junge and GAO Qiang. A Fast Computing Method of N-1 in Static Safety Analysis Considering BATS in Regional Power Grid[J]. Automation of Electric Power Systems, 2015, 39(24): 122-128
Authors:PAN Kaiyan  TAN Dashuai  ZHAO Yong  LI Junge  GAO Qiang
Affiliation:Dongfang Electronics Corporation, Yantai 264000, China,Dongfang Electronics Corporation, Yantai 264000, China,Dongfang Electronics Corporation, Yantai 264000, China,Guangzhou Power Supply Bureau, Guangzhou 510620, China and Guangzhou Power Supply Bureau, Guangzhou 510620, China
Abstract:Many busbar automatic transfer switches (BATSs) will be triggered by N-1 analysis because of their own characteristics of a regional power grid. In the traditional method, a specific failure is simulated first, then the topology analysis is made and finally the topology analysis considering BATS operation is made. The whole process involves frequent switch operation, so a great deal of topology calculation is needed. Two real-time N-1 calculation methods considering BATS are proposed based on the characteristics of the regional power grid. In these methods, BATS operation is simulated by the load transfer method in the flow check process by means of power supply path search or pre-building the mapping relation between N-1 fault and actuating BATS. As the method does not have to change the topology information of the power grid, it can significantly reduce calculating time. Field operation shows that the proposed method is feasible and better able to perform N-1 analysis for the power grid.
Keywords:static safety analysis   N-1   load transformation   busbar automatic transfer switch (BATS)   power supply path search
本文献已被 CNKI 等数据库收录!
点击此处可从《电力系统自动化》浏览原始摘要信息
点击此处可从《电力系统自动化》下载全文
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号