华能瑞金电厂2号锅炉钢结构顶板大梁吊装技术
引用本文:柯胜金,王劲.华能瑞金电厂2号锅炉钢结构顶板大梁吊装技术[J].工程质量,2008(21).
作者姓名:柯胜金  王劲
作者单位:重庆电力建设总公司;
摘    要:在江西华能瑞金电厂2×350MW超临界机组2号锅炉钢结构顶板大梁吊装中,顶板大梁共有5根,编号分别为A、B、C、D、E,其中A、B、E三根梁采取一台吊车独立吊装;C、D两根梁因单重超过最大起重机械额定负荷50t,采取FZQ1250与80t滑车组抬吊,D梁在炉顶通过小坦克平移就位,C梁直接抬吊就位。

关 键 词:发电厂  锅炉钢结构  顶板大梁  吊装技术

Hoisting Technology of Steel Roof and Beam for No.2 Boiler in Huanengruijin Power Station
KE Sheng-jin WANG Jin.Hoisting Technology of Steel Roof and Beam for No.2 Boiler in Huanengruijin Power Station[J].Quality of Civil Engineering and Construction,2008(21).
Authors:KE Sheng-jin WANG Jin
Affiliation:KE Sheng-jin WANG Jin(Chongqing head company of electric power construction,Chongqing 400060)
Abstract:In the hoisting of steel roof and beam for 2×350MW over-critical mechanical unit No.2 boiler in Huanengruijin power station,there are 5 beams which the number is A,B,C,D,E respectively.The beam A,B and C was hoisted independently by one crane.Because of the weight of beam C or D exceed the 50t upper limit of load of single crane,therefore,FZQ1250 and 80 pulley set crane was used to let beam D move horizontally to its position by over the little tank,and the beam C move to its position directly.
Keywords:power station  steel structure of boiler  roof and beam  hoisting technology  