兰渝铁路桃树坪隧道3号斜井进正洞施工技术
引用本文:赵旭鹏.兰渝铁路桃树坪隧道3号斜井进正洞施工技术[J].华北水利水电学院学报,2012(1):119-122.
作者姓名:赵旭鹏
作者单位:中铁十三局集团有限公司
摘    要:大断面隧道施工中,斜井进正洞衔接段施工是工程的重点和难点之一.在建的兰渝铁路桃树坪隧道位于第三系粉细砂层中,地下水位在洞顶2 m以上,为双线大断面饱和沙土隧道.以桃树坪隧道3#斜井进入正洞段施工为例,详细介绍了大断面饱和沙土隧道由斜井进入正洞施工技术,为类似工程施工提供参考.

关 键 词:隧道工程  饱和砂土地层  主洞与斜井交叉段  施工技术

Construction Technology of No.3 Inclined Shaft of Taoshuping Tunnel into the Main Tunnel of the Railway from Lanzhou to Chongqing
ZHAO Xu-peng.Construction Technology of No.3 Inclined Shaft of Taoshuping Tunnel into the Main Tunnel of the Railway from Lanzhou to Chongqing[J].Journal of North China Institute of Water Conservancy and Hydroelectric Power,2012(1):119-122.
Authors:ZHAO Xu-peng
Affiliation:ZHAO Xu-peng(China Railway 13th Bureau Group Co.Ltd.,Changchun 130033,China)
Abstract:In the process of large cross-section tunnel construction,the linking-up section construction of inclined shaft into the main tunnel is one of the important difficulties of the project.Taoshuping tunnel of the railway from Lanzhou to Chongqing is located in Tertiary fine sand layer,and the groundwater level is more than 2 meters above the tunnel roof.It is a double large cross-section saturated sand tunnel.Taking the construction of No.3 inclined shaft of Taoshuping tunnel into the main tunnel as an example,the construction technology of inclined shaft into the main tunnel of the large cross-section saturated sand tunnel is described in detail,which can provide a reference for the similar project construction.
Keywords:tunnel project  saturated sand layer  intersection of main tunnel and inclined shaft  construction technology