斜框构桥顶进施工的顶镐布置分析
引用本文:王旭东. 斜框构桥顶进施工的顶镐布置分析[J]. 山西建筑, 2010, 36(7): 327-329
作者姓名:王旭东
作者单位:太原铁路局工务处,山西,太原,030013
摘    要:通过对斜交框构桥与正交框构桥顶进施工的对比,找出两者的不同点,对斜交框构桥顶进时的转动问题进行了受力分析,又对千斤顶布置的三种方式进行了对比分析,并结合工程实例,通过理论计算,解决了斜交框构斜向顶进时的转动问题,使框构桥正确就位。

关 键 词:斜框构桥  顶进  千斤顶不对称布置

Arrangement analysis on jacking construction for oblique frame-shaped bridge
WANG Xu-dong. Arrangement analysis on jacking construction for oblique frame-shaped bridge[J]. Shanxi Architecture, 2010, 36(7): 327-329
Authors:WANG Xu-dong
Affiliation:WANG Xu-dong
Abstract:Through the comparison between the construction technology oblique-crossing frame-shaped bridge and normal-crossing frame-shaped bridge,this paper finds out their differences,carries out force analysis on the rotation in the course of oblique frame-shaped bridge jacking and the contrastive analysis on three ways of arranging the jacking equipments,and combined with project examples,it has solved the rotating problem concerning the jacking of the oblique-crossing frame by theoretical calculation,putting the frame-shaped bridge in the right place.
Keywords:oblique frame-shaped birdge  jacking  unsymmetrical arrangement of the jacking equipment