顶推法拆除连续梁桥导梁的设计及施工
引用本文:张伟锋. 顶推法拆除连续梁桥导梁的设计及施工[J]. 山西建筑, 2013, 0(31): 166-168
作者姓名:张伟锋
作者单位:[1]长沙理工大学,湖南长沙410000 [2]广东省长大公路工程有限公司,广东广州514265
摘    要:结合佛开高速改扩建工程实例,介绍了顶推法拆除旧北江大桥主桥的方法,着重对顶推法施工中导梁的设计、施工及拼装方案进行了研究,并阐述了导梁的静载试验技术,为顺利进行主桥顶推过程提供了科学依据。

关 键 词:导梁  顶推法  拆除  安装

The design and construction using incremental launching method demolition of continuous beam bridge guide beam
ZHANG Wei-feng. The design and construction using incremental launching method demolition of continuous beam bridge guide beam[J]. Shanxi Architecture, 2013, 0(31): 166-168
Authors:ZHANG Wei-feng
Affiliation:ZHANG Wei-feng1,2 (1. Changsha University of Science and Technology, Changsha 410000, China; 2. Guangdong Changda Highway Engineering Limited Company, Guangzhou 514265, China)
Abstract:Combining with the reconstruction and extension project of Fo-Kai highway, this paper introduced the method of using incremental launching method demolition of old North River bridge, emphatically researched the guide beam design, construction and erection method in in- cremental launching method construction, and elaborated the static load test technique of guide beam, provided scientific basis for smooth main bridge incremental launching process.
Keywords:guide girder   incremental launching method   demolition   installation