日臻完善的高塔简易组立工艺
引用本文:梁志伟.日臻完善的高塔简易组立工艺[J].广东输电与变电技术,2007(2):45-48.
作者姓名:梁志伟
作者单位:广东省输变电工程公司
摘    要:在输电线路大跨越工程施工中,对100m以上的高塔组立,应根据高塔设计特点和施工现场的实际情况,确定最佳的施工方案。在500kV肇庆站至花都站送电线路工程的大跨越高塔SZK-345施工中,采用钢管扒杆进行组立,安全高效完成,重点介绍其施工工艺流程和组立方法的特点。

关 键 词:大跨越  钢管扒杆  高塔组立

A Excelsior Method easy to Establish High Tower
Liang Zhiwei.A Excelsior Method easy to Establish High Tower[J].Guangdong Power Transmission Technology,2007(2):45-48.
Authors:Liang Zhiwei
Affiliation:Guangdong Power Transmission and Substation Engineering Co.Liang Zhiwei
Abstract:To do the construction of power transmission line great span object,for establish the high tower,if its height is over 100m,the optimal construct method should be fixed on according to the design features of the high tower and the practical situation in site,In SZK-345 great span high tower construction of 500kV transmission line from Zhaoqing substation to Huadu substation, which is establish by means of the tilled mast tube,and completed safely/efficiently.The technology process of this construction and the characteristic of the group-standing method are introduced in detail.
Keywords:Great span  Tilled mast tube  High tower establish