引用本文:陈炼. 麻石水电站1号水轮发电机组增容改造初步设计[J]. 红水河, 2010, 29(3): 18-20,28
作者姓名:陈炼
作者单位:广西电力工业勘察设计研究院,广西,南宁,530023
摘    要:麻石水电站1号机组经过37年的运行,机组各部件老化严重,安全隐患较大,进行技术改造非常有必要,文章介绍了麻石水电站1号机组增容改造选型的方案及水轮机主要参数的选择。经过技术改造后,1号机的单机容量可提高至36.5 MW,比原机组增容30.3%。

关 键 词:水轮发电机  改造  选型设计  麻石水电站

Preliminary Design for Capacity Enlargement and Transformation of 1# Hydroelectric Generating Unit at Mashi Hydropower Station
CHEN Lian. Preliminary Design for Capacity Enlargement and Transformation of 1# Hydroelectric Generating Unit at Mashi Hydropower Station[J]. Hongshui River, 2010, 29(3): 18-20,28
Authors:CHEN Lian
Affiliation:CHEN Lian(Guangxi Electric Power Industry Investigation Design and Research Institute,Nanning 530023)
Abstract:Mashi Hydropower Station's 1# unit has aged after 37 years of service, and shall be provided with technical transformation.The scheme of capacity enlargement and transformation of 1# unit and selection of main parameters for the water turbine are discussed.The unit capacity of 1# unit adds to 36.5MW after technical transformation,an increase of 30.3% compared with the original capacity.
Keywords:hydroelectric generating unit  transformation  type selection design  Mashi Hydropower Station