摘    要:介绍巴江口水电站溢流坝采用宽尾墩戽式消力池联合消能的试验研究成果,试验表明:该联合消能型式能较好解决巴江口水电站的大单宽流量、低佛氏数的泄洪消能问题,减轻下游河床、岸坡的冲刷,确保船闸下游安全通航。

关 键 词:宽尾墩  戽式消力池  消能效果  巴江口水电站
修稿时间:1998-12-07)

Research and test for united dissipation of energy of the wide tail pier-bucket typed stilling pool of the Bajiangkou hydropower station
Gan Huiqi,Ling Xianzong,Li Xia. Research and test for united dissipation of energy of the wide tail pier-bucket typed stilling pool of the Bajiangkou hydropower station[J]. Gx Water Resources & Hydropower Engineering, 1999, 0(2): 19-21
Authors:Gan Huiqi  Ling Xianzong  Li Xia
Abstract:This paper introduced the result of research and test for UDEWSP of the Bajiangkou HS . The test proved that UDEWSP solved better the problem of energy dissipation . And so reduces the erosion of downstream bed and bank and ensures the lock shipping safely .
Keywords:wide tail pier    bucket typed stilling pool    energy dissipation effect   the Bajiangkou HS