首页 | 本学科首页   官方微博 | 高级检索  
     

嘉兴电厂2号炉LCS装置的技术改进
作者单位:嘉兴发电厂!浙江省平湖市乍浦,314201
摘    要:嘉兴电厂2号炉空气预热器的漏风控制装置,经过这次大修清除了原存在的一些缺陷并作了部分改进,平均漏风率下降6.5%,使左、右侧平均漏风率达到10.53%。取得较好效果,

关 键 词:空气预热器  漏风控制装置  改进效果

Technical Improvement of Leakage Control System(LCS)Device for Boiler #2 of Jiaqing Power Plant
Tao Jun. Technical Improvement of Leakage Control System(LCS)Device for Boiler #2 of Jiaqing Power Plant[J]. Boiler Technology, 1998, 0(10)
Authors:Tao Jun
Abstract:After the overhaul, some original defects were removed and technical improvements were made for LCS of air preheater in boiler # 2 of Jiaxing Power Plant, and good resultsare obtained that average leakage rate of left and right sides reaches 10.53%, with 6.5%reduced.
Keywords:Air preheater LCS Improvement results
本文献已被 CNKI 等数据库收录!