土压平衡盾构法施工参数的模型试验研究
引用本文:朱合华,徐前卫,廖少明,傅德明,于宁.土压平衡盾构法施工参数的模型试验研究[J].岩土工程学报,2006,28(5):553-557.
作者姓名:朱合华  徐前卫  廖少明  傅德明  于宁
作者单位:同济大学岩土工程重点实验室地下建筑与工程系;上海隧道工程股份有限公司;同济大学岩土工程重点实验室地下建筑与工程系 上海200092;安徽理工大学土木工程系;安徽淮南232001;上海200092;上海200233;
基金项目:国家科技攻关项目;上海市学科科研项目
摘    要:由于受地质条件和施工工艺的限制,盾构掘削参数的变化难免会对地层产生扰动影响,往往由此而引发一系列的环境病害问题,故而有必要开展土体-盾构系统的基础试验研究。首先进行了盾构模型试验方案的设计,该方案包括直径0.4 m的土压平衡模型盾构、2.4 m×2.4 m×1.2 m的试验土箱、盾构工作驱动系统和数据采集系统等4部分;随后在软硬不同的模型土层中,进行盾构不同工作参数组合的掘削试验,得出一些有用的规律。

关 键 词:模型试验  土压平衡盾构机  土体-盾构系统  
文章编号:1000-4548(2006)05-0553-05
收稿时间:2005-04-30
修稿时间:2005-04-30

Experimental study on working parameters of EPB shield machine
ZHU He-hua,XU Qian-wei,LIAO Shao-ming,FU De-ming,YU Ning.Experimental study on working parameters of EPB shield machine[J].Chinese Journal of Geotechnical Engineering,2006,28(5):553-557.
Authors:ZHU He-hua  XU Qian-wei  LIAO Shao-ming  FU De-ming  YU Ning
Affiliation:1.Key Laboratory of Geotechnical Engineering Department of Geotechnical Engineering Tongji University Shanghai 200092 China 2.Department of Civil Engineering Anhui University of Science and Technology Huainan 232001 China 3.Shanghai Research Institute of Tunnel Construction Technique Shanghai 200233 China
Abstract:Due to the limitation of geologic condition and construction technology,the advance of shield machine would disturb stratum inevitably,which could induce a series of environmental problems.For better understanding the relationship between the soil working parameters of machine and the perturbation characteristics of stratum,it is necessary to start the elementary experiment researches on ground-shield machine system.Therefore,a special test scheme was designed firstly for this purpose.It included:(1) A model of earth pressure balance shield machine with diameter of 0.4 m;(2) A soil box with dimension of 2.4 m×2.4 m×1.2 m;(3) Control system of driving and rotating;(4) Computer-aided data collection system.Subsequently,in hard and soft model stratum respectively,various working parameters of machine were combined for tunneling test.Based on the test results,some useful rules were drawn.
Keywords:model test  earth pressure balance shield machine  ground-shield machine system