PERT 21: Fitting PERT/CPM for use in the 21st century
Authors:Dan Trietsch  Kenneth R. Baker
Affiliation:1. College of Engineering, American University of Armenia, Yerevan, Armenia;2. Tuck School, Dartmouth College, Hanover NH, USA
Abstract:More than half a century after the debut of CPM and PERT, we still lack a project scheduling system with calibrated and validated distributions and without requiring complex user input. Modern decision support systems (DSS) for project management are more sophisticated and comprehensive than PERT/CPM. Nonetheless, in terms of stochastic analysis, they show insufficient progress. PERT 21 offers a radically different stochastic analysis for projects, based on relevant and validated theory. Operationally, it is sophisticated yet simple to use. It is designed to enhance existing DSS, and thus it can be implemented without sacrificing the investment already made in project management systems. Finally, regarding the important sequencing and crashing models developed under CPM, PERT 21 permits their adaptation to stochastic reality.
Keywords:PERT/CPM   Stochastic project scheduling   Planning and control   Project management decision support systems (DSS)   Critical Chain
本文献已被 ScienceDirect 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号