首页 | 本学科首页   官方微博 | 高级检索  
     

苏只水电站水轮机安装高程的确定
引用本文:张延锋,MA Guo-qiang.苏只水电站水轮机安装高程的确定[J].西北水电,2008(2):53-55.
作者姓名:张延锋  MA Guo-qiang
作者单位:中国水电顾问集团西北勘测设计研究院,西安,710065
摘    要:以黄河上游苏只水电站为例,对轴流转桨式与灯泡贯流式2种机型进行分析,详细讨论确定低水头径流式电站水轮机安装高程新的经济方法,并论证其合理性,突出下游设计尾水位的选取,抬高了安装高程。

关 键 词:径流式电站  水轮机  安装高程  方案比选

Determination of turbine setting elevation for Suzhi HPP
ZHANG Yan-feng,MA Guo-qiang.Determination of turbine setting elevation for Suzhi HPP[J].Northwest Water Power,2008(2):53-55.
Authors:ZHANG Yan-feng  MA Guo-qiang
Affiliation:ZHANG Yan- feng, MA Guo - qiang ( Northwest Hydro Consulting Engineers, CHECC, Xi'an 710065)
Abstract:Taking the Suzhi HPP on the Yellow River as an example, this paper analyzes the 2 types of axial flow Kaplan turbine and bulb tubular turbine, and discusses in detail the new economic method for determination of turbine setting elevation for low head run - of- river plant. By highlighting the selection of downstream tailrace level, the setting elevation was raised.
Keywords:run - of - river plant  turbine  setting elevation  option selection
本文献已被 维普 万方数据 等数据库收录!
设为首页 | 免责声明 | 关于勤云 | 加入收藏

Copyright©北京勤云科技发展有限公司  京ICP备09084417号