首页 | 本学科首页   官方微博 | 高级检索  
     

漳泽电厂1号和2号机关停对长治电网的影响
引用本文:贾蕾. 漳泽电厂1号和2号机关停对长治电网的影响[J]. 山西电力, 2008, 0(2): 10-12
作者姓名:贾蕾
作者单位:长治供电分公司,山西,长治,046011
摘    要:基于电网现状进行潮流计算,对漳泽电厂机组关停引发的一系列问题进行分析,提出长治北部电网运行方式(包括检修方式)调整方案及应对措施,为电网规划提供依据。

关 键 词:电网  运行方式  对策  规划
文章编号:1671-0320(2008)02-0010-03
修稿时间:2007-12-07

Influence of Changzhi Network Made by Zhangze Power Plant NO.1 and No.2 Unit Shutoff
JIA Lei. Influence of Changzhi Network Made by Zhangze Power Plant NO.1 and No.2 Unit Shutoff[J]. Shanxi Electric Power, 2008, 0(2): 10-12
Authors:JIA Lei
Affiliation:JIA Lei (Changzhi Power Supply Company, Changzhi, Shanxi 046011, China)
Abstract:Based on the power flow calculation in the circumstances of electric network,a series of issues generated by the close of Zhangze electric units are analyzed,adjustment measures and suggestions of run manner of northern Changzhi network,including service manner are put forward,which proposes conditions to electric network plan.
Keywords:electric network  running manner  effective measure  plan