山南水库大坝加固方案优化
引用本文:原玉英 陈志刚. 山南水库大坝加固方案优化[J]. 山西水利科技, 2000, 0(1): 45-46
作者姓名:原玉英 陈志刚
作者单位:水利部山西水利水电勘测设计研究院(原玉英),阳泉市水利局(陈志刚)
摘    要:本文针对山南水库大坝除险加固方案进行了方案比选 ,使加固后的坝体既能达到结构稳定又能从根本上解决浸润线过高的问题

关 键 词:大坝加固 土工膜 水库 方案优化

Dam Strengthening of Shannan Reservoir
Yuan Yuying Chen Zhigang. Dam Strengthening of Shannan Reservoir[J]. Shanxi Hydrotechnics, 2000, 0(1): 45-46
Authors:Yuan Yuying Chen Zhigang
Affiliation:Yuan Yuying Chen Zhigang
Abstract:Shannan Reservoir completed in 1974,lies in Shannan River,the branch of Tao River,it had once some problems in its earth dam quality,such as percolating from dam slope downstream,poor compactness of the dam body,high phreatic line in the dam and clogging of inverted filter in the dam toe.In the light of these problems,two main dam strengthening schemes were proposed.In this paper,the content of the dam strengthening schemes is introduced.The scheme selected finally,in brief,is a scheme that the composite geomemebrane is paid on dam surface upstream,it has not only solved all the problems metioned above,but saved about 300,000 Yuan.Now,the reservoir is being operated well since the dam strengthening project was completed in Sept.1999.The height of the earth dam and the total capacity of the reservoir being 40 m and 5,350,000 m 3 respectively.
Keywords:Dam Strengthening Geomembrane