隆林布东水电站引水隧洞进、出口段开挖及支护
引用本文:梁天津. 隆林布东水电站引水隧洞进、出口段开挖及支护[J]. 广西水利水电, 2006, 0(1): 58-60,65
作者姓名:梁天津
作者单位:广西水利电力勘测设计研究院,广西,南宁,530023
摘    要:介绍隆林布东水电站引水隧洞在开挖及支护施工过程中,针对隧洞进、出口段的实际情况,结合工程地质条件,采用相应的开挖及支护措施.

关 键 词:引水隧洞  开挖  支护  工程地质
文章编号:1003-1510(2006)01-0058-03
收稿时间:2006-02-22
修稿时间:2006-02-22

Excavation, support and protection of diversion tunnel inlet and outlet sections of Budong HPP
LIANG Tian-jin. Excavation, support and protection of diversion tunnel inlet and outlet sections of Budong HPP[J]. Gx Water Resources & Hydropower Engineering, 2006, 0(1): 58-60,65
Authors:LIANG Tian-jin
Affiliation:Guangxi Water and Power Design Institute, Nanning 530023, China
Abstract:In the course of excavation, support and protection construction of diversion tunnel of Budong Hydropower Plant at Longlin county, corresponding excavation, support and protection measures were taken according to the actual conditions of tunnel inlet and outlet sections as well as the engineering geological conditions.
Keywords:Diversion tunnel   excavation   support and protection   engineering geology