论工程网络图中多余虚箭线的判定及去除方法
引用本文:罗明. 论工程网络图中多余虚箭线的判定及去除方法[J]. 土木与环境工程学报, 2001, 23(2): 51-55
作者姓名:罗明
作者单位:重庆大学B区建设管理与房地产学院,
摘    要:在深入分析双代号网络中虚箭线生成过程的基础上,提出了针对不同具体问题类型判断及去除网络图中多余虚箭线的方法,其意义是有助于工程网络计划编制人员迅速识别并有效去除网络图中的多余虚箭线。

关 键 词:网络图 多余虚箭线 施工活动 网络计划
文章编号:1006-7329(2001)02-0051-05
修稿时间:2000-07-05

Methods of Determining and Deleting Additional Dummy Arrows in Network Diagram
LUO Ming. Methods of Determining and Deleting Additional Dummy Arrows in Network Diagram[J]. Journal of Civil and Environmental Engineering, 2001, 23(2): 51-55
Authors:LUO Ming
Abstract:Based on analysis of the function of dummy arrow in network diagram, this paper provides some methods to determine and delete additional arrows. It will be helpful to personnel in engineering network planning for determining and deleting the additional dummy arrows quickly and correctly.
Keywords:network diagram  additional dummy arrows  duplicate  replacement  deletion