阳城电厂水处理系统浮床的优化调整试验
引用本文:文晋元. 阳城电厂水处理系统浮床的优化调整试验[J]. 山西电力, 2002, 0(4): 35-38
作者姓名:文晋元
作者单位:阳城国际发电有限责任公司,山西 阳城 048100
摘    要:针对阳城电厂浮床周期制水量达不到设计要求,且运行工况不良的现象,通过分析再生液浓度、再生用酸碱量以及其它条件对浮床运行的影响,并在大量的实验基础上,找到了造成这一现象的原因是树脂填装量不足。

关 键 词:阳城电厂 水处理系统 浮床 优化调整 试验 树脂
文章编号:1671-0320(2002)04-0035-04
修稿时间:2001-06-28

Optimizing and Debugging of Water Treatment System Floatiog Bed in Yangcheng Power Plant
WEN Jin yuan. Optimizing and Debugging of Water Treatment System Floatiog Bed in Yangcheng Power Plant[J]. Shanxi Electric Power, 2002, 0(4): 35-38
Authors:WEN Jin yuan
Abstract:In this article the problem was found that water made quantity in a cycle of floating bed can't meet the design request,and the operation condition isn't good.Based on a mass of experiment and through analyzing the condition impacts on the floating bed such as regenerating solution concentration,acid and alkali quantity used in regenerating solution and so on.Based on large amount of experements,It is found that the reason caused this phenomenon is that resin filled in is insufficiency.
Keywords:water treatment  floating bed  optimizing operation  