首页 | 本学科首页   官方微博 | 高级检索  
     

公伯峡水电站有压段衬砌混凝土的设计与施工
引用本文:王思德.公伯峡水电站有压段衬砌混凝土的设计与施工[J].水力发电,2004,30(8):41-42.
作者姓名:王思德
作者单位:黄河上游水电开发有限责任公司建设分公司,青海,化隆,810902
摘    要:全段面钢模台车进行圆形隧洞混凝土衬砌的施工方法首次在公伯峡水电站中应用。公伯峡水电站左岸泄洪洞为有压隧洞,采用全段面钢模台车施工,简要介绍了左岸泄洪洞圆形压力隧洞混凝土衬砌的设计与施工情况,保证了洞衬混凝土的质量,但仍存在一些问题需改进。

关 键 词:泄洪洞  全段面钢模台车  混凝土工程  施工  公伯峡水电站
文章编号:0559-9342(2004)08-0041-02

Design and construction of the lined concrete in the pressured section of left-bank flood-releasing tunnel for Gongboxia Hydropower Station
Wang Si de.Design and construction of the lined concrete in the pressured section of left-bank flood-releasing tunnel for Gongboxia Hydropower Station[J].Water Power,2004,30(8):41-42.
Authors:Wang Si de
Abstract:The flood releasing turned in the left bank of Gongboxia Hydropower station is a pressure tunnel. It will introduce the design and the condition of construction of circular concrete lined tunnel. In the water power project of upstream of the Yellow River, it is the first that adopting the construction method which conducting circular concreter lined tuned by full face jack plane, and it can gain the fine benefits. But it also needs improve some defects.
Keywords:rush down  the whole sections steel mould car  Building concrete  construction  Gongboxia Power Station