首页 | 本学科首页   官方微博 | 高级检索  
     

桥电五期125MW机组锅炉安全门保护无法正常投运的原因分析及改进
引用本文:陈杰.桥电五期125MW机组锅炉安全门保护无法正常投运的原因分析及改进[J].青海电力,2001(1):23-25.
作者姓名:陈杰
作者单位:青海省桥头发电厂
摘    要:1998年初改造前,桥电五期2×125MW机组投产后锅炉安全门保护装置长期不能正常投入运行,文章对其设计、安装、设备等方面存在的问题进行了详细分析,并提出了改进措施。

关 键 词:锅炉  安全门  保护  运行  125MW机组  发电厂
修稿时间:2001年2月28日

Analysis and lmprovement of the Boiler Safety Gate Protection which can not Operate Normally of the 125MW Unit in the Fifth Phase of Qiaotou Thermal Power
Chen jie.Analysis and lmprovement of the Boiler Safety Gate Protection which can not Operate Normally of the 125MW Unit in the Fifth Phase of Qiaotou Thermal Power[J].Qinghai Electric Power,2001(1):23-25.
Authors:Chen jie
Abstract:Before the improvement at the beginning of the year 1998,the boiler gate protection equipment of the 2×125MW unit in the fifth phase of Qiaotou thermal power plant can not operate normally for a long time after it puts into operation,the paper makes a detailed analysis about the present problems in its design,installation and equipment etc and proposes some improvement measures.
Keywords: